Application of stud welding in the construction of Shanghai global financial center

Views:4611     Release time:2020-01-04 16:20:52

Shanghai global financial center
 
 
 
The specification of welding studs in Shanghai World Financial Center is Φ 19 × 100. There are either direct welding studs on steel beams or through welding studs. All the 1-80 layers are stud welded by KOCO welding machine. After 80 floors, it is higher than the nearby Jinmao Building and becomes the tallest building in Shanghai. At the expert review meeting on the standard of technical specification for stud welding, the experts on the construction of Shanghai global financial center put forward to me: the construction of the global center will soon enter the lightning season, can we provide "lightning proof stud welding machine"? After many months of research and development, our institute has successfully developed the "lightning bolt welding machine" and applied it to the bolt welding of more than 80 layers in Shanghai global finance. More than 3000 bolts are welded in each layer, about 60000 in total. The welding machine not only meets the needs of bolt welding, but also has the function of lightning protection. It is highly praised by the user: Shanghai Construction Engineering Group and China Construction Third Engineering Bureau. Shanghai global financial center stud penetration welding verification statistical report 101 project Shanghai Construction Supervision Company Supervision and steel structure quality director of China Construction Third Engineering Bureau on site supervision, designated special personnel to inspect 1000 consecutive stud welded by imported welding machine and Chengdu star welding machine, and 10 stud welded in a group. (there are only 99 groups missing in tabulation, and 990 welding joints are inspected for each welding machine.) The statistical results of visual inspection, bending inspection and inclination inspection are as follows:
 
Test content: rst-2500-3, a German brand
 
One time qualification rate: 84%, 89.80%
 
Bending qualification rate: 90.50%, 94.50%
 
Tilt qualification rate 94% 97%
 
The number of pores below 3 accounts for 5.10% and 2.30%
 
Conclusion: the first pass rate is more than 89.8%, the bend pass rate is more than 94.5%, the tilt pass rate is more than 97%, and the number of pores under 3 is less than 2.3%. According to the statistics of the qualified rate of stud penetration welding quality, the domestic stud welding equipment and technology have reached a high level.